01473 257671Contact usMembers Area
Basildon & Thurrock University Hospital roof with Bauder Total Roof System and LiquiTEC cold applied waterproofing system installed

Basildon & Thurrock University Hospital

Bauder Total Roof System (BTRS) and LiquiTEC cold applied waterproofing system

Project Type:
Refurbishment
Sector:
Healthcare
System:
Reinforced Bitumen Membrane, Cold Applied Liquid
Location:
East of England

Synopsis

Basildon and Thurrock University Hospital’s existing roof was failing in multiple areas, and 80 rooflights needed replacing. The client wanted the refurbishment to make as little impact as possible on the departments directly below which included drug refrigeration, x-ray and ultrasound clinics, patient wards and operating theatres.

  • Basildon & Thurrock University Hospital roof with Bauder Total Roof System and LiquiTEC cold applied waterproofing system installed
  • Bauder KSD Duo being installed
  • 2 men working together to install Bauder roofing products on roof
  • Basildon & Thurrock University Hospital roof with Bauder Total Roof System and LiquiTEC cold applied waterproofing system installed
  • Basildon & Thurrock University Hospital roof with Bauder Total Roof System and LiquiTEC cold applied waterproofing system installed
  • Basildon & Thurrock University Hospital roof with Bauder Total Roof System and LiquiTEC cold applied waterproofing system installed

Bauder Building Board

Project

Basildon & Thurrock University Hospital

TypeRefurbishment
LocationEssex
Roof size

900 m²

SpecifierNHS
Approved contractor

Breyer Construction

Products applied

LiquiDETAIL:
Cold applied liquid fast-curing waterproofing resin, for use on upstands and details.

Project challenges

The plant on the rooftop could not be turned off or raised and many of the AC units and boilers had to be left running due to the nature of the rooms below. Certain areas had to be repaired before others and detailing under and around the plant that could not be raised was almost an impossible task. When working around the plant, COSHH regulations had to be considered and adhered to.

The result 

Coordinating with both the client and approved contractors was key in this project, and by using cold liquid applied waterproofing the contractors could ensure a watertight seal with quick application, allowing them to complete the remainder of the roof using reinforced bitumen membrane, and meet the tight project deadline of 12 weeks.

System Build Up

Bauder Total Roof System (BTRS) and LiquiTEC Cold-applied Waterproofing System

Bauder Total Roof System (BTRS)

Bauder Total Roof System (BTRS)

Our long-established Bauder Total Roof System (BTRS) incorporates elastomeric bitumen membranes for strength and durability on flat roofs.

Visit our Technical Centre for more information
Thickness (mm)5.2
Weight (kg/m2)0.25
LiquiTEC Cold Applied Waterproofing System

LiquiTEC Cold Applied Waterproofing System

The Bauder LiquiTEC roof system is a fast-curing poly methyl methacrylate (PMMA) resin system reinforced with polyester fleece.

Visit our Technical Centre for more information

Advocacy

Breyer Roofing’s Contracts Manager for the project, Kerry Cutts:

“The main challenge was working around the hospital’s requirements. For example, we provided a weekly plan for the areas we were working in and the rooflights / plant affected. Where possible, we worked out of hours while doing rooflight replacements to minimise any issues. We also worked closely with Bauder to vary the specification when we had to work around live plant. The communication between Bauder and Breyer Roofing was exemplary throughout and I was pleased this completed project was nominated for a national award."